[Oct-2023] The The Open Group OG0-092 Exam Test For Brief Preparation Revolutionary Guide To Exam The Open Group Dumps The Open Group OG0-092: TOGAF 9 Part 2 exam is designed to test the knowledge of enterprise architects who have already taken the TOGAF 9 Part 1 exam. It is the second level of certification in the TOGAF 9 certification program. TOGAF 9 Part 2 certification validates the skills necessary [...]

[Oct-2023] The The Open Group OG0-092 Exam Test For Brief Preparation [Q38-Q58]

Share

[Oct-2023] The The Open Group OG0-092 Exam Test For Brief Preparation 

Revolutionary Guide To Exam The Open Group Dumps


The Open Group OG0-092: TOGAF 9 Part 2 exam is designed to test the knowledge of enterprise architects who have already taken the TOGAF 9 Part 1 exam. It is the second level of certification in the TOGAF 9 certification program. TOGAF 9 Part 2 certification validates the skills necessary to implement and manage the TOGAF framework within an organization. OG0-092 exam is globally recognized and is a great way to enhance your career in enterprise architecture.


Unit 21: Architecture Partitioning

The students need to have competency in:

  • describing how Architecture Partitioning can be utilized in the framework of the ADM Preliminary Phase.
  • describing the Architecture Partitioning purpose;
  • describing the classification criteria for architectures & solutions when considering partitioning;

The Open Group OG0-092 (TOGAF 9 Part 2) Certification Exam is a globally recognized certification exam that validates the knowledge and skills of an individual in the field of enterprise architecture. TOGAF 9 Part 2 certification is offered by The Open Group, a leading global consortium that develops and maintains various industry standards in IT and enterprise architecture. The OG0-092 exam is the second part of the TOGAF 9 certification program and builds upon the concepts and principles covered in Part 1.

 

NEW QUESTION # 38
Scenario: Summer Seeds BV
Please read this scenario prior to answering the question
Summer Seeds BV is an international agricultural company exporting bulbs, flowers and seeds worldwide. It is headquartered in Rotterdam in the Netherlands, and has sales and distribution centers in over 60 countries worldwide. Several of these centers include administrative, manufacturing, and research facilities. To achieve full integration of their research capabilities with their development centers located in various climate zones, the company wants to develop strong self directed teams in each location. It also wants to define new business models that are profitable while reducing their impact on the environment. The management is deeply committed to ensuring that the company is a world leader in socially responsible seed development with a business strategy that focuses on profitability through environmentally friendly operating processes. Summer Seed's international operations are subject to various legal and regulatory requirements. In areas such as genetically modified seeds, governmental controls are strictly enforced and compliance is critical. Recently a competitor was heavily fined for violating the regulations in a country where it was developing pest-resistant seeds. The Governing Board is concerned, and as a result has approved the expenditure of resources to establish an Enterprise Architecture program. They have requested information about the status of projects that could impact regulatory compliance. They also want to enable the corporate legal staff and auditors to analyze proposed architectures to ensure that they are within the legal guidelines for a given location. In addition, the research organization should be able to see that the architecture is appropriate for its needs. TOGAF 9 has been mandated as the guiding framework for the development and evolution of the Enterprise Architecture practice.
Refer to the Summer Seeds BV Scenario
You have been appointed as the Lead Consultant. You have been asked to recommend an approach that would enable the development of an architecture that addresses the needs of all these parties. Based on TOGAF 9, which of the following is the best answer?

  • A. Depending on the nature of the architecture, a set of models should be created that can be used to ensure that the system will be compliant with the local regulations. Stakeholders should be able to view the models to see that their concerns have been properly addressed.
  • B. Each architecture activity should be developed using a consistent modeling approach that is uniform across all architecture projects. Each architecture should be defined based on this fixed set of models so that all concerned parties can examine the models to ensure that their issues and concerns have been addressed,
  • C. For those groups that have sufficient power and level of interest, a special report should be created that summarizes the key features of the architecture with respect to the particular location. Each of these reports should reflect the stakeholders' requirements.
  • D. A stakeholder map should be developed that allows the architects to define groups of stakeholders sharing common concerns. A set of views should then be defined that addresses the concerns for each group-Architecture models can then be created for each view to address the stakeholders' concerns.

Answer: A


NEW QUESTION # 39
Scenario: Marona Inc.
Marona Inc is a Fortune 500 Enterprise in the retail industry with retail store components manufacturing units
and marketing outlets spanning the globe and having an annual turnover of 20 billion$ with more than 100, 000
employees world wide.
The CEO, CIO and the stakeholders of the ongoing EA projects are concerned about rising costs and as one
measure want to do an investigation into the operational aspects of the realized Enterprise Architecture using
TOGAF9.
The CIO approaches you as the Lead Enterprise Architect to carry out this exercise the stakeholder had voiced
to him the following concerns:
They want to analyze the roles of the top management for each revenue earning service. Moreover, many of
the HR related critical Search application component have become extremely slow. This needs to be
diagnosed and rectified. Moreover there is no proper tracking of revenue from retail store component products
over time. There has also been a lot of unauthorized or unwanted access to many of the critical information.
Hence the mode of access needs to be strengthened and made much more secure. Another additional
concern is the new launches and the progress of each of the launches over time.
Determine which of the following set of viewpoints are most appropriate to analyze and view in order to address
this concern of the stakeholders.

  • A. (i) System/Functions Matrix
    (ii) Actor/Role Matrix
    (iii) Data Entity/Business Function Matrix
    (iv) Technology Portfolio Catalog
    (v) Data Security Diagram
  • B. (i) Location Catalog
    (ii) Service/Function Catalog
    (iii) Data Entity/Business Function Matrix
    (iv) Application Communication Diagram
  • C. (i) System/Functions Catalog
    (ii) System/Technology Matrix
    (iii) Goal/Objective/Service Diagram
    (iv) Product Life Cycle Diagram
    (v) Data Security Diagram
  • D. (i) Goal/Objective/Service Diagram
    (ii) Contract Measure Catalog
    (iii) Data Dissemination Diagram
    (iv) Application Communication Diagram
    (v) Data Life Cycle Diagram

Answer: C


NEW QUESTION # 40
SureFlight Air Carrier has received approval for the acquisition of a regional carrier.
To integrate the new acquisition, a TOGAF based enterprise architecture program has been initiated. The CIO
sponsors the activity supported by the Chief Architect.
In Phase A within the initial iteration the CIO wants to ensure that the architecture activities are recognized
among the various stakeholders of the enterprise.
Refer to the scenario above
You are a consultant supporting the Chief Architect that should explain how to identify and engage the
stakeholders at this stage of the program.
Identify the best answer accordingly to the TOGAF 9 guidelines.
Choose one of the following answers

  • A. You first priority is to communicate with the regional carrier stakeholders developing a Communications
    Plan to share main features and discuss opportunities with them.
  • B. You identify all the main stakeholders on both the acquired carrier and the rest of the enterprise. Using a
    stakeholder map, you classify and record their power in relation to this activity. You then focus on
    implementing the relevant viewpoints that can address the concerns of every main stakeholder identified in
    the stakeholders map.
  • C. You conduct a pilot proof of concept during Phase A to demonstrate the technical feasibility to the
    stakeholders explaining the approach available from your preferred suppliers.
  • D. Using the business scenarios technique you would identify supporting and not supporting stakeholders.
    Then you would list the set of viewpoints that are addressing the stakeholder concerns and share these
    with them.

Answer: B


NEW QUESTION # 41
Magic Wand Corporation manufactures a range of equipment used by magician worldwide. The global popularity of a series of children's books describing the formative years of a budding wizard and his various escapades at wizard school has driven unprecedented sales growth in the magical equipment market.
The current IT systems at Magic Wand are struggling to cope with the high volumes in this growth market.
The CIO wants to persuade the board of Magic Wand Corporation to make a greater investment in the IT systems to cope with the new higher transaction volumes. On of the key components the CIOs wants to include when he approaches the board is a description of the current problems and how they may be addressed from an architectural point of view.
As the High Architect of Magic Wand Corporation, the CIO has delegated the task of creating a vision for the future Architecture to you.
Which of the following answers best describes how TOGAF recommends delivering an Architecture Vision for the CIO?

  • A. I would start by establishing the architecture project and follow the appropriate project management method. I would identify stakeholders their concerns and business requirements then confirm and elaborate the business goals, business drivers and constraints. I would then evaluate the business capabilities and readiness for business transformation and define the scope. I would then develop the architecture vision, define the target architecture value proposition, KPIs and identify and mitigate all risks associated with the transformation effort. Finally, I would develop an Enterprise Architecture Plan and Statement of Work and secure approval from the relevant stakeholders.
  • B. Firstly, I ensure there is a Request for Architecture Work from the CIO. Then I ensure that there is recognition for the architecture vision project by following any project management and programmed management frameworks used within the organization. I would identify the key stakeholders and engage with them to understand and document their concerns and high-level requirements. This would result in a stakeholder map used to support other deliverables such as the Architecture Vision, a Communications plan and a Statement of Architecture Work. I would then identify the business goals and strategic drivers of the organization and define any enterprise or project specific constraints such as time and resources. I would then define the business capabilities of the organization needed to fulfill those business goals and drivers and their readiness for change. Once complete, I would define the scope, confirm the architecture and business principles and develop the Architecture Vision. Following this, I would define the business case for the architecture project, assess the business risks and produce a risk mitigation plan. I would then define a plan of enterprise architecture work to meet the scope in the desired time line and the resources required and secure the support of stakeholders.
  • C. I would approach this by defining and establishing the architecture team and governance. This would be followed by agreeing and establishing the architecture principles. I would select and customize an architecture framework changing any terminology and selecting the right phases and customizing the structure of content and outputs from the chosen method. Finally I would select and implement and architecture tools. The outputs from this work would include an Organization Model for Enterprise Architecture, a Tailored Architecture Framework including method and content, the Architecture Principles, an initial architecture repository, restatement or references to business principles, business goals and business driver, a request for architecture work and the governance framework.
  • D. I would start by ensuring there is a Request for Architecture Work from the sponsor (the CIO). I would then create a project to define and deliver the architecture vision and the necessary outputs. The outputs include an approved Statement of Architecture Work, refined statements of Businesses Principles, Business Goals and Business Drivers, Architecture Principles, a Capability Assessment, a Tailored Architecture Framework, an Architecture vision, a Communications plan. The Statement of Architecture Work needs to be clear on the scope of architectural work, the resources needed to complete the work and amount of time it would take to complete the work assuming the scope of architectural work is agreed and that all the resources required are available. The final step would be to agree the Statement of Architectural Work with stakeholders confirming the scope, schedule and confirming the availability of the necessary resources.

Answer: B


NEW QUESTION # 42
Scenario: AGEX Inc.
Please read this scenario prior to answering the question
AGEX is a large, global commodities trading company which has been growing rapidly through a series of acquisitions.
Each new business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information.
The inability to share information across businesses has resulted in lost opportunities to "leverage the synergies" that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, AGEX has begun implementing a single Enterprise Resource Planning (ERP) system to consolidate information from several applications that exist across the lines of business. The Corporate Board is concerned that the new ERP system must be able to manage and safeguard customer information in a manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services offered to clients and trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the ERP implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Review Board to oversee and govern the architecture.
After reviewing the available alternatives, and based on recommendations from the ERP vendor, AGEX has selected TOGAF 9 as the basis for its Enterprise Architecture program.
The CIO has endorsed this choice with the full support of top management.
Refer to the AGEX Inc. Scenario
You are serving as the Chief Architect.
As part of the process for establishing the Enterprise Architecture department, you have decided to create a set of principles to guide the activities.
You have been asked to recommend the best approach for this work.
Based on TOGAF 9, which of the following is the best answer?

  • A. You examine the mission statements for AGEX and each of its businesses, together with the corporate value statements. Based on that, you work with the Architecture Review Board to define the principles.
    When developing the principles you ensure that they actively promote the alignment of IT with the AGEX business strategies. You then run a series of reviews with all the relevant stakeholders, including senior management, ensuring their support.
  • B. You examine the mission statements for AGEX and each of its businesses, together with the corporate value statements. Based on that, you define a set of principles and review with the CIO.
    When developing the principles you ensure that they actively promote the alignment of IT with the business strategies and initiatives of AGEX. You then seek the endorsement of the CIO and senior management.
  • C. You define a set of principles that support the preferred best practices embodied in the Enterprise Architecture department charter. You publish the principles on the corporate intranet to ensure widespread acceptance and compliance.
    You then schedule regular periodic Compliance Assessments with individual business units to check that they have made satisfactory progress toward meeting the objectives and conditions embodied in the principles.
  • D. You gather information from credible industry sources in the commodities business. Based on that, you assess current trends and apply that to defining a set of principles that embody best practices.
    You select architecture principles that do not conflict with each other and that should be stable. You ensure that all the principles are realistic and avoid including principles that are obvious.

Answer: A

Explanation:
Explanation


NEW QUESTION # 43
Scenario
Please read this scenario prior to answering the question
You have been assigned the role of Lead Enterprise Architect for a firm that is a major OEM parts supplier to the auto industry. Europe has been the primary market for its products, with just 20% of its output being exported to North America. The firm is planning to expand its exports to North America and also to establish sales in South America and the Asia Pacific region. This will enable them to better ride out recessions in key markets such as Europe. It will also enable the firm to exploit the auto industry move to global platforms.
The firm is organized into business units with each addressing different auto industry sectors. Each business unit has acquired other procedures to expand its manufacturing capacity. This has resulted and manufacturing systems.
The Enterprise Architecture (EA) program within the firm has been functioning for several years. It has made significant progress in consolidating the technology portfolio and establishing key standards. The CIO and the COO are joint sponsors of the EA program. The EA program is mature, with an Active Architecture Board and a well-defined architecture process and standard content templates based on the TOGAF Architecture Content Framework. The EA program is well coordinated with Project Management Office, Systems Development, and Operations functions.
The firm has completed a strategic plan to reorganize its Sales & Marketing organization according to the target geographic markets. One of the goals of this reorganization is to improve the ability of Marketing to collect more meaningful market analytics that will enable each sector to better address market needs with effective marketing campaigns and global product presence.
A Request for Architecture Work to address the goals of the reorganization has been approved. As the architecture team commences its work, the CIO has expressed concerns about whether the firm will be able to adapt to the proposed change and how to manage the associated risks.
Refer to the Scenario
You have been asked how to address the concerns of the CIO.
Based on the TOGAF standard, which of the following is the best answer?

  • A. In Phase A, the team should conduct a Business Scenario to describe the business problem, identify the stakeholders' and the resulting retirements. Once the requirements have been identified, they can be assessed in terms of their risks. The risks should be evaluated in terms of how they could be avoided, transferred, or mitigated. Any risks that cannot be resolved should be identified as residual risks and their disposition should be decided by the Architecture Board.
  • B. In Phase A, the team should evaluate the organization's readiness to undergo change. This will identify the factors that will influence the reorganization. This should include a maturity scale that will allow the team to gauge the urgency, readiness, and degree of difficulty to fix. These factors can then be used to assess the initial risks associated with the proposed project.
  • C. In Phase A, the team should analyze their risk by completing an Implementation Factor Assessment and Deduction Matrix to identify the particular risks associated with the implementation and deployment. The matrix should include a list of factors to be considered, their descriptions, and constraints that should be taken into account. These factors can then be used to assess the initial risks associated with the proposed project.
  • D. In Phase B, the team should create a set of views that will enable them to identify the factors that will influence the successful reorganization. There should then be an assessment of each factor on a maturity scale that will allow the team to gauge the urgency, readiness, and degree of difficulty to fix. These factors can then be used to assess the initial risks associated with the proposed project.

Answer: A


NEW QUESTION # 44
Scenario: Rollins Manufacturing
Please read this scenario prior to answering the question
Rollins Manufacturing is a major supplier in the automotive industry, headquartered in Cleveland, Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of these plants has been operating its own Manufacturing Requirements Planning (MRPII) system, production scheduling, and custom developed applications that drive the automated production equipment at each plant.
Rollins is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current MRPII and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff.
The Rollins Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9.At a recent meeting, the Architecture Review Board approved a Request for Architecture Work from the Chief Engineer of Global Manufacturing Operations who is the project sponsor. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of driving their MRPII and production scheduling from a central system located in Cleveland. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Rollins Manufacturing Scenario:
You are serving as the Lead Enterprise Architect for the Common ERP Deployment architecture project.
One of the earliest initiatives in the Enterprise Architecture program at Rollins was the definition of a set of IT principles and architecture principles that are well aligned with the overall enterprise principles. These now need to be updated to address the concerns raised.
You have been asked to select a set of principles most appropriate for guiding the team to define a robust solution.
[Note: You should assume that Rollins has adopted the example set of principles that are listed and defined in TOGAF 9, Section 23.6.]
Based on TOGAF 9, which of the following is the best answer?

  • A. Common-use Applications, Data is Shared, Data is Accessible, Data is Secure, Interoperability, Control Technical Diversity.
  • B. Information Management is Everybody's Business, IT Responsibility, Data Trustee, Technology Independence, Responsive Change Management.
  • C. Maximize Benefit to the Enterprise, Business Continuity, Common-use Applications, Data is Shared, Data is Accessible, Data is Secure.
  • D. Business Continuity, Service-orientation, Data is Accessible, Data is Secure, Responsive Change Management.

Answer: C


NEW QUESTION # 45
Scenario: AGEX Inc.
Please read this scenario prior to answering the question
AGEX is a large, global commodities trading company which has been growing rapidly through a series of acquisitions.
Each new business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information. The inability to share information across businesses has resulted in lost opportunities to "leverage the synergies" that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, AGEX has begun implementing a single Enterprise Resource Planning (ERP) system to consolidate information from several applications that exist across the lines of business. The Corporate Board is concerned that the new ERP system must be able to manage and safeguard customer information in a manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services offered to clients and trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the ERP implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Review Board to oversee and govern the architecture.
After reviewing the available alternatives, and based on recommendations from the ERP vendor, AGEX has selected TOGAF 9 as the basis for its Enterprise Architecture program.
The CIO has endorsed this choice with the full support of top management.
Refer to the AGEX Inc. Scenario
You are serving as the Chief Architect.
You have been asked to recommend the approach to take in the Preliminary Phase to ensure that the Corporate Board's concern is addressed.
Based on TOGAF 9, which of the following is the best answer?

  • A. You evaluate the implications of the Board's concern in terms of regulatory and security policy requirements. You then update the AGEX security policy to reflect the concern, ensuring that this policy is communicated across the organization.
    You allocate a security architecture team to ensure that security considerations are included in ongoing architecture planning. You then assess the security implications and agreements within the AGEX businesses and their suppliers.
  • B. You start by clarifying the intent that the Board has for raising this concern. This enables you to understand the implications of the concern in terms of regulatory requirements and the potential impact on current business goals and objectives.
    You propose that a security architect or security architecture team be allocated to develop comprehensive security architecture.
  • C. You evaluate the implications of the Board's concern by examining the potential impacts on business goals and objectives. Based on your understanding, you then update the current AGEX security policy to include an emphasis on the Board's concern.
    In addition, you allocate a security architect to ensure that security considerations are included in the architecture planning for all domains.
  • D. You evaluate the implications of the Board's concern in terms of regulatory requirements and their impact on business goals and objectives. Based on this understanding, you then issue a Request for Architecture Work to commence an architecture development project to develop a solution that will address the Board's concern.
    You allocate a security architect to oversee the implementation of the solution in the ERP system that is being developed.

Answer: A


NEW QUESTION # 46
Scenario
Please read this scenario prior to answering the question
Your role is that of a consultant to the Lead Enterprise Architect in a company that develops photovoltaic technologies for use in large-scale solar power farms. The company has three manufacturing facilities, two in the United States, and one in Southern France. Each of these facilities supplies a different manufacturer that assembles and sells complete systems. The solar panels and photovoltaic arrays are custom engineered to meet each manufacturer's design specifications.
A challenge that the solar power industry has faced is the efficiency of energy conversion. When a conventional solar panel overheats, it becomes inefficient and generates less energy. In response to this, the research arm of the company has pioneered the development of a new solar panel design that will produce up to 50% more energy than standard solar panels when operating at elevated temperatures. This will allow the production of significantly more useable energy per square meter than from standard solar technology. This new design is ready to go into production.
The company has a mature Enterprise Architecture practice that is supported by a cross-functional Architecture Board. TOGAF 9 is used for developing the automated manufacturing process and systems used to design, manufacture and test the solar power technologies they produce. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
As part of putting the new solar panel design into production, a pilot architecture project at a single location has defined an updated standard approach for controlling the automated test systems used to perform final quality assurance. The Chief Engineer, sponsor of the activity, and the Architecture Board have approved the plan for immediate implementation at each plant.
Architecture Contracts have been developed that detail the work needed to implement and deploy the new automated test system controller for each location. The Chief Engineer has expressed concern that a uniform process be employed at each location to ensure consistency and high yields.
Refer to the Scenario
The Lead Enterprise Architect has asked you to recommend the best approach to address the Chief Engineer's concern.
Based on TOGAF, which of the following is the best answer?

  • A. You create an Architecture Contract to manage and govern the implementation and migration process at each location. For internal development projects, you issue a memorandum of understanding between the Architecture Board and the implementation organization. For contracts issued to an external party, you ensure that it is a fully enforceable legal contract.
    You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
  • B. You create an Architecture Contract to manage and govern the implementation and migration process.
    If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Architecture Board and the implementation organization.
    You recommend that if a deviation from the Architecture Contract is detected, the Architecture Board grant a dispensation to allow the implementation organization the ability to customize the process to meet their local needs.
  • C. You use the Architecture Contracts to manage the architecture governance processes for the project across the locations. You deploy monitoring tools to assess the performance of each completed solar panel assembly at each location and develop change requirements if necessary.
    You recommend that if a deviation from the contract is detected, the Architecture Board should modify the Architecture Contract to allow the implementation organization the ability to customize the process to meet their local needs. As a result, you then issue a new Request for Architecture Work to implement the modified Architecture Definition.
  • D. You review the applicable Architecture Contract for each location, ensuring that it addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management. In cases where the contract is issued to an external party, you ensure that it is a legally enforceable contract.
    You schedule compliance reviews at key points in the implementation process to ensure that the work is proceeding in accordance with the Architecture Definition. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.

Answer: B


NEW QUESTION # 47
Scenario: Glacier Ridge LLC
Please read this scenario prior to answering the question
Glacier Ridge LLC is a vacation property management firm that is growing through acquisition. It manages over 200 resort properties across North America. Many of the resort properties use the same internal IT systems that they used before they were acquired. Until recently, the only requirement that has been placed en each property is that they use a standard financial reporting system to report their financials ID the headquarters on a weekly basis. The CEO has stated his concerns about the inefficiencies of the current approach and identified the need to change. He has defined a new strategic vision that will enhance the Glacier Ridge property business by standardizing its operations across the network to provide consolidated financial, human resources, logistics, sales and marketing, and yield management. He has also stated that he expects results by the end of the current fiscal year. These changes will provide the company with improved utilization of its capacity and more efficient operations. The addition of a corporate-wide data warehouse will provide analytics that will enable the marketing group to improve its ability to target advertising into key markets to improve yields. Glacier Ridge has mature enterprise architecture (EA) practice and uses TOGAF 9 as the method and guiding framework.
The CIO is the sponsor of the activity. In planning this change, the Chief Architect engaged the services of a well-known consulting firm that specializes in business strategy. An initial study has been conducted to identify the strategic changes needed to implement the CEO's vision. This recently completed with approval of a strategic architecture encompassing the entire firm, including detailed requirements and recommendations.
Based on the recommendations from the initial engagement, Glacier Ridge has embraced an Architecture Vision to adopt an enterprise application that is tailored to the needs of the hospitality industry.
Refer to the Glacier Ridge scenario
Your role is that of Chief Architect. You have been asked to recommend the best approach to take in this architecture engagement to realize the CEO's vision. Based on TOGAF 9, which of the following is the best answer?

  • A. Since the vision is well understood and the strategic architecture agreed, you recommend that the target architecture is defined first, followed by transition planning. This will ensure that the current inefficiencies of the baseline architecture are not carried forward, and that the proposed solution addresses the requirements identified in the initial architecture engagement.
  • B. You recommend that this engagement define the Technology Architecture first in order to assess the current infrastructure capacity and capability. Then the focus should be on transition planning and architecture deployment. This will identify requirements to ensure that the projects are sequenced in an optimal fashion so as to realize the vision.
  • C. Since the initial engagement has identified the need to change, you recommend that the team focus on defining the target architecture by going through the architecture definition phases (B-D). This will ensure that the change can be defined in a structured manner and address the requirements needed to realize the vision.
  • D. You recommend that the team focus on architecture definition, with a specific emphasis on understanding the strategic change parameters of the business strategy. Once understood, the team will be in the best position to identify the requirements, drivers, issues, and constraints for this engagement.
    You would ensure that the target architecture addresses non-functional requirements so as to help forecast future impacts.

Answer: D


NEW QUESTION # 48
Scenario:
Please read this scenario prior to answering the question
Your role is consultant to the Lead Architect within a company that manufactures a variety of small electromechanical devices. The company is organized as independent operational divisions.
The company has a mature Enterprise Architecture practice and uses TOGAF standard for the basis of its architecture framework. In addition to the EA program, the company has a number of management frameworks in use, including business planning, portfolio/project management, and operations management.
The EA program is sponsored by the CIO.
Each division has completed the Architecture Definition documentation required to tailor and configure the environment to meet its own specific manufacturing requirements.
The enterprise architects have analyzed the key corporate change attributes and implementation constraints. A consolidated gap analysis has been completed which has identified the gaps across the Business, Data, Application, and Technology domains. Based on the results of the gap analysis, the architects have reviewed the requirements, dependencies and interoperability requirements needed to integrate the new ERP environment into the existing environment. The architects have completed the Business Transformation Readiness Assessment started in Phase A. Based on all of these factors they have produced a risk assessment.
The implementation process is estimated to take four years. Because of the risks posed by the complexity of the current environment, a phased approach is needed to implement the target architectures. The implementation and Migration Plan v0 1, the draft Architecture Roadmap, and the Capability Assessment deliverables are now complete.
Refer to the Scenario
You have been asked to recommend the next steps to prepare the final Implementation and Migration Plan.
Based on TOGAF standard, which of the following is the best answer?

  • A. You would place the strategic Architecture Definition and Transition Architectures under configuration control as part of the ongoing architecture development cycle. This will ensure that the architecture remains relevant and responsive to the needs of the enterprise. You would then produce an Implementation Governance Model to manage the lessons learned prior to finalizing the plan. You recommend that lessons learned be accepted by the Architecture Board as changes to the architecture without review.
  • B. You would assess how the plan impacts the other frameworks in use in the organization. The plan should be coordinated with the business planning, portfolio/project management and operations management frameworks. You would then assign a business value to each project, considering available resources and priorities for the projects. Finally, you would generate the Implementation and Migration Plan.
  • C. You would apply the Business Value Assessment Technique to prioritize the implementation projects and project increments. The assessment should focus on return on investment and performance evaluation criteria that can be used to monitor the progress of the architecture transformation. You would confirm the Transition Architecture phases using an Architecture Definition Increments Table to list the projects. You would then document the lessons learned and generate the final plan.
  • D. You would conduct a series of Compliance Assessments to ensure that the implementation team is implementing the architecture according to the contract. The Compliance Assessment should verify that the implementation team is using the proper development methodology. It should include deployment of monitoring tools and ensure that performance targets are being met. If they are not met, then changes to performance requirements should be identified and updated in the Implementation and Migration Plan.

Answer: B


NEW QUESTION # 49
Scenario
Please read this scenario prior to answering the question
Your role is that of Lead Enterprise Architect working at the headquarters of a fast food chain. The chain manages over 7500 restaurants across 33 countries. Each restaurant in the chain is an independently owned and operated franchise.
Many of the restaurants still use the first generation IT systems deployed over 10 years ago. The Chief Operating Officer (COO) of the chain has stated his concerns about the inefficiencies of the current systems and identified the need to change. He has defined a new strategic vision that will enhance the business including providing its franchisees new support services to help them address the increasing competition from coffee shops. This is part of the long-term commitment to enhance the brand image and increase revenue for the chain. He has also stated that he expects improved financial results by the end of the current fiscal year.
The changes will help provide the chain with improved products, including healthier alternatives in the menu, and more efficient operations. The addition of a corporate-wide data warehouse will provide analytics that will enable the marketing group to improve its ability to target advertising and new products to specific regions.
The chain has a mature Enterprise Architecture practice based in its headquarters and uses the TOGAF standard as the method and guiding framework. The CIO is the sponsor of the activity.
In planning the change, the Chief Architect engaged the services of a well-known consulting firm that specializes in business strategy. An initial study has been conducted to identify the strategic changes needed to implement the COO's vision. This recently completed with approval of a strategic architecture encompassing the entire chain, including detailed requirements and recommendations.
Based on the recommendations from the initial study, the decision has been taken for the chain to adopt a packaged suite of integrated applications that is tailored to the needs of the franchise.
Refer to the scenario
You have been asked by the Chief Architect to propose the best approach for architecture development to realize the COO's vision.
Based on the TOGAF standard, which of the following is the best answer?

  • A. You propose that the focus be placed on architecture definition, with emphasis on understanding the strategic change parameters. The requirements, drivers, issues, and constraint for this engagement can then be identified. You would ensure that the target architecture addresses non-functional requirements so as to ensure the target architecture is robust and secure.
  • B. You propose that the baseline Technology Architecture is defined first in order to assess the current infrastructure capacity and capability. Then the focus should be on transition planning and architecture deployment. This will identify requirements to ensure that the projects are sequenced in an optimal fashion so as to realize the vision.
  • C. You propose that the target architecture is defined first, followed by transition planning. This is because the vision is well understood and the strategic architecture agreed. The target first approach will ensure that the current problems and inefficiencies of the baseline architecture are not carried forward, and that the proposed solution addresses the requirements identified in the initial study.
  • D. You propose that the target architecture is defined first by going through the architecture definition phases (B-D). This is because the initial study identified the need to change. This will ensure that the change can be defined in a structured manner and address the requirements needed to realize the vision.

Answer: C


NEW QUESTION # 50
Scenario: Vittronics Ltd.
Please read this scenario prior to answering the question Vittronics Ltd. is a leading medical device manufacturer in the highly competitive market for Migraine Headache Pain Management (MHPM) devices. These tiny wireless devices are implanted in the brain and can deliver a precise electric shock when the wearable Pain Control Unit (PCU) detects an increase in stress induced by the onset of a migraine headache.
This technology will be a breakthrough in the treatment of this condition, and several competitors are striving to be the first to introduce a product into the market. However, all of them must demonstrate the effectiveness and safety of their products in a set of clinical trials that will satisfy the regulatory requirements of the countries in the target markets.
The Enterprise Architecture group at Vittronics has been engaged in an architecture development project to create a Secure Private Immersive Collaborative Environment (SPICE) that will allow researchers at its product development laboratories worldwide to share information about their independent clinical trials.
The Vittronics Enterprise Architecture group is a mature organization that has been utilizing TOGAF for several years. They have recently upgraded to TOGAF 9. The Vittronics Architecture Development Method (VADM) is strictly based on the TOGAF 9 Architecture Development Method (ADM) with extensions required to support current good manufacturing practices and good laboratory practices in their target markets.
The SPICE project team has now completed the Business, Information Systems, and Technology Architecture phases and has produced a complete set of deliverables for each phase. Due to the highly sensitive nature of the information that is managed in SPICE, special care was taken to ensure that each architecture domain included an examination of the security and privacy issues that are relevant for each domain. A corresponding SPICE Security Architecture has been defined.
The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity. He has stated that the changes to the SPICE architecture will need to be rolled out on a geographic basis that will minimize disruptions to ongoing clinical trials. The work will need to be done in stages and rolled out in geographical regions.
Refer to the Vittronics Ltd Scenario
You are serving as the Lead Architect for the SPICE project team.
You have been asked to recommend the approach to identify the work packages that will be included in the Transition Architecture(s).
Based en TOGAF 9, which of the following is the best answer?

  • A. Group the Solution Building Blocks from a Consolidated Gaps, Solutions and Dependencies Matrix into a set of work packages. Using the matrix as a planning tool, regroup the work packages to account for dependencies. Sequence the work packages into the Capability Increments needed to achieve the Target Architecture. Schedule the rollout one region at a time. Document the progression of the enterprise architecture using an Enterprise Architecture State Evolution table.
  • B. Determine the set of Solution Building Blocks required by identifying which Solution Building Blocks need to be developed and which need to be procured. Eliminate any duplicate building blocks. Group the remaining Solution Building Blocks together to create the work packages using a CRLO matrix. Rank the work packages in terms of cost and select the most cost-effective options for inclusion in a series of Transition Architectures. Schedule the roll out of the work packages to be sequential across the geographic regions.
  • C. Create an Implementation Factor Assessment and Deduction Matrix and a Consolidated Gaps, Solutions and Dependencies Matrix. For each gap, identify a proposed solution and classify it as new development, purchased solution, or based on an existing product. Group similar solutions together to form work packages. Identify dependencies between work packages factoring in the clinical trial schedules. Regroup the packages into a set of Capability Increments scheduled into a series of Transition Architectures and documented in an Architecture Definition Increments Table.
  • D. Use a Consolidated Gaps, Solutions and Dependencies Matrix as a planning tool. For each gap classify whether the solution is either a new development, purchased solution, or based on an existing product. Group the similar solutions together to define the work packages. Regroup the work packages into a set of Capability Increments to transition to the Target Architecture taking into account the schedule for clinical trials.

Answer: C


NEW QUESTION # 51
Scenario: Global Mobile 1
Please read this scenario prior to answering the question
Global Mobile is a mobile telecommunications company formed through a series of mergers and acquisitions. They are yet to fully integrate the customer service systems for the most recent acquisitions, and as result, customer service has been a major concern for the Chief Technology Officer.
Results for the last two quarters have shown that Average Revenue Per User (ARPU) and the customer retention (Churn) rate have fallen below the industry average. The Corporate Marketing group has published some new findings about customer satisfaction. The customers appear to be switching to Air Light, a competitor, because of superior customer service. Global Mobile actually has better coverage in nearly all markets than Air Light, and good roaming agreements that keep rates low for business travelers.
But, customer satisfaction has remained low.
The Business Strategy group and the Enterprise Architecture group have conducted a high-level project to develop the enterprise-wide strategic plan. They have developed a business scenario which contains a good conceptual model of what needs to be done, and also identifies the key requirements. This was used in preparing the proposal presented to the Executive Council and the Corporate Board.
The planning for the program has been underway for several months. Global Mobile has selected TOGAF
9 as the basis for its Enterprise Architecture.
The Corporate Board has approved funding for a multi-million Euro conversion to transition to a packaged Customer Service System. It is anticipated that the overall program will take five years to complete, but there are some tactical projects that can commence immediately to address the situation. The Corporate Board has placed one additional major constraint on the program. In addition to achieving the business outcomes directly related to improving overall customer service within each business unit, the Corporate Board expects the Target Architecture to produce an additional saving of at least 30% over current operating costs through energy efficiency initiatives, virtualization of servers and workstations, and expanded telecommuting and desk-sharing. This Green initiative is intended to become a model for future investments at all company facilities worldwide.
Refer to Global Mobile scenario
You have been engaged as a consultant to advise the Chief Architect on the best ways to approach to the implementation planning activities for this significant business transformation.
Based on TOGAF 9, which of the following is the best answer? (Is this the right answers to choose?)

  • A. You recommend using conventional implementation planning techniques. The Capability-Based Planning approach is normally only used in public sector, defense-related programs. This approach is not appropriate for a private sector company.
  • B. The Capability-Based Planning approach used in the organization's TOGAF-based Enterprise Architecture framework is focused on business outcomes. The Green initiative is an infrastructure program that is technical in nature; therefore, it would not be appropriate to use the Capability-Based Planning approach. Instead, the Global Mobile systems development lifecycle approach should be utilized to develop the Solution Architecture.
  • C. You recommend that the implementation planning activities be conducted using Capability-Based Planning. This is appropriate because the Green initiative is an enterprise-wide plan with a horizontal scope. Its metrics are aggregated at the enterprise level. It is crucial to gain business unit support and cooperation to achieve the broader business outcomes which will benefit all.
  • D. You recommend using conventional implementation planning techniques. The horizontal scope of the Green initiative would make the Capability-Based Planning approach used in the organization's TOGAF-based Enterprise Architecture framework difficult to manage and govern. This approach to planning was better applied within the vertical scope of a business unit.

Answer: C


NEW QUESTION # 52
Scenario
Please read this scenario prior to answering the question
You are serving as the Lead Architect for an insurance company, which has been formed through the merger of three previously independent companies. The company now consists of three divisions with the same names and division headquarters as their predecessors.
The lack of integration between the three divisions has increasingly caused problems in the handling of customer and financial information. The inability to share information has resulted in lost opportunities to
"leverage the synergies" that had been intended when the company was formed. At present, each division maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, and claims information, each division has different ways of defining these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, the company has made the decision to introduce a common web portal, contact center software suite, and document management system. Also the company has selected a single enterprise-wide customer relationship management (CRM) application to consolidate information from several applications that exist across the divisions. The application will be used by each of the divisions and accessed by third party partners through well defined interfaces.
The Corporate Board is concerned that the new application must be able to manage and safeguard confidential customer information in a secure manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services in cooperation with its partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the implementation team and the migration teams in each division. The CIO has also formed a cross-functional Architecture Board to oversee and govern the architecture. The company has an existing team of security architects.
TOGAF 9 has been selected as the core framework for use for the Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management.
Refer to the Scenario
In the Preliminary Phase you need to define suitable policies and ensure that the company has the appropriate capability to address the concerns of the Corporate Board.
Based on TOGAF, which of the following is the best answer?

  • A. You evaluate the implications of the Board's concerns by examining the security and regulatory impacts on business goals, business drivers and objectives. Based on your understanding, you then update the current security policy to include an emphasis on the concerns. You define architecture principles to form constraints on the architecture work to be undertaken in the project. You then allocate a security architect to ensure that security considerations are included in the architecture planning for all domains.
  • B. You evaluate the implications of the concerns raised by the Corporate Board in terms of regulatory requirements and their impact on business goals and objectives. Based on this understanding, you then issue a Request for Architecture Work to commence an architecture development project to develop a solution that will address the concerns. You allocate a security architect to oversee the implementation of the new application that is being developed.
  • C. You identify and document the security and regulatory requirements for the application and the data being collected. You ensure that written policies are put in place to address the requirements, and that they are communicated across the organization, together with appropriate training for key employees.
    You identify constraints on the architecture and communicate those to the architecture team. You establish an agreement with the security architects defining their role within the ongoing architecture project.
  • D. You start by clarifying the intent that the Board has for raising these concerns. This enables you to understand the implications of the concerns in terms of regulatory requirements and the potential impact on current business goals and objectives. You propose that a security architect or security architecture team be allocated to develop a comprehensive security architecture and that this be considered an additional domain architecture.

Answer: A


NEW QUESTION # 53
Scenario:
Please read this scenario prior to answering the Question
You are serving as the Chief Architect for a large, global commodities trading company which has been growing rapidly through a series of acquisitions.
Each business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information. The inability to share information across businesses has resulted in lost opportunities to "leverage the synergies" that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, the company has made the decision to introduce a single enterprise-wide application to consolidate information from several applications that exist across the lines of business. The application will be used by all business units and accessed by suppliers through well defined interfaces.
The Corporate Board is concerned that the new application must be able to manage and safeguard confidential customer information in a secure manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services in cooperation with its trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Board to oversee and govern the architecture. The company has an existing team of security architects.
TOGAF 9 has been selected for use for the Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management.
Refer to the Scenario
In the Preliminary Phase you need to define suitable policies and ensure that the company has the appropriate capability to address the concerns of the Corporate Board.
Based on TOGAF 9, which of the following is the best answer?

  • A. You identify and document the security and regulatory requirements for the application and the data being collected. You ensure that written policies are put in place to address the requirements, and that they are communicated across the organization, together with appropriate training for key employees.
    You identify constraints on the architecture and communicate those to the architecture team. You establish an agreement with the security architects defining their role within the ongoing architecture project.
  • B. You evaluate the implications of the Board's concerns by examining the security and regulatory impacts on business goals, business drivers and objectives. Based on your understanding, you then update the current security policy to include an emphasis on the concerns. You define architecture principles to form constraints on the architecture work to be undertaken in the project. You then allocate a security architect to ensure that security considerations are included in the architecture planning for all domains.
  • C. You evaluate the implications of the concerns raised by the Corporate Board in terms of regulatory requirements and their impact on business goals and objectives. Based on this understanding, you then issue a Request for Architecture Work to commence an architecture development project to develop a solution that will address the concerns. You allocate a security architect to oversee the implementation of the new application that is being developed.
  • D. You start by clarifying the intent that the Board has for raising these concerns. This enables you to understand the implications of the concern in terms of regulatory requirements and the potential impact on current business goals and objectives. You propose that a security architect or security architecture team be allocated to develop a comprehensive security architecture and that this be considered an additional domain architecture.

Answer: A


NEW QUESTION # 54
Scenario: Rollins Manufacturing
Please read this scenario prior to answering the question
Rollins Manufacturing is a major supplier in the automotive industry, headquartered in Cleveland, Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of these plants has been operating its own Manufacturing Requirements Planning (MRPII) system, production scheduling, and custom developed applications that drive the automated production equipment at each plant.
Rollins is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current MRPII and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff.
The Rollins Enterprise Architecture department has been operating for several years and has mature, well- developed architecture governance and development processes that are strongly based on TOGAF 9.At a recent meeting, the Architecture Review Board approved a Request for Architecture Work from the Chief Engineer of Global Manufacturing Operations who is the project sponsor. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of driving their MRPII and production scheduling from a central system located in Cleveland. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Rollins Manufacturing Scenario
You are serving as the Lead Enterprise Architect of the newly-formed Common ERP Deployment architecture project team.
As the Common ERP Deployment architecture project team assembles for its initial meeting, many of the participants have voiced concerns about the sweeping scope of the initiative. Others are confident that they know a solution that will work. During the meeting, a number of alternative recommendations for how to proceed are put forward by members of the team.
You have been asked to select the most appropriate recommendation to ensure that the team evaluates different approaches to the problem and clarifies the requirements for the architecture.
Based on TOGAF 9, which of the following is the best answer?

  • A. The team should create Baseline and Target Architectures for each of the manufacturing plants. A gap analysis between the architectures will then validate the approach, and determine the Transition Architecture needed to achieve the target state.
  • B. The team should exercise due diligence and carefully research vendor literature and conduct a series of briefings with vendors that are on the current approved supplier list. Based on the findings from the research, the team should define a preliminary target Architecture Vision. The team should then use that model to build consensus among the key stakeholders.
  • C. The team should conduct a pilot project that will enable vendors on the short list to demonstrate potential solutions that will access the concerns of the stakeholders. Based on the findings of that pilot project, a complete set of requirements can be developed that will arrive the evolution of the architecture.
  • D. The team should hold a series of interviews at each of the manufacturing plants using the business scenario technique. This will then enable them to identify and document the characteristics of the architecture from the business requirements.

Answer: D


NEW QUESTION # 55
Scenario
Please read this scenario prior to answering the question
You are serving as the Lead Architect for the enterprise architecture team at a large multinational aerospace and defense company. The company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems. Several procurement processes have had problems related to the timing of purchases, which has led to excess inventory. The Vice President in charge of Supply Chain Management has made the decision to consolidate and reduce redundant procurement processes and systems.
The company will move to a "Just-in-time" procurement system so as to keep inventory costs low.
TOGAF 9 is used for internal Enterprise Architecture activities. This project is using an iterative approach for executing the Architecture Development Method (ADM).
At present, there are no particularly useful architectural assets in the Architecture Repository that are related to this initiative. All assets will need to be acquired, customized, or created from scratch. The company prefers to implement commercial off the shelf package applications with little customization. The CIO, who is the project sponsor, has stated that she is not concerned about preserving the existing procurement processes or systems.
The architecture development project has completed the Preliminary Phase and has started a number of iteration cycles to develop the Architecture. As a packaged application is being considered, the next iteration will include both the Business and Application Architectures. Key stakeholder concerns that should be addressed by these architectures include:
1. What groups of people should be involved in procurement-related business processes?
2. What are the overall lifetimes of the Request for Proposal and Purchase Order business objects?
3. What non-procurement applications will need to be integrated with any new procurement applications?
Refer to the Scenario
[Note: You may need to refer to Chapter 35 of the reference text in order to answer this question.] You have been asked to identify the most appropriate catalogs, matrices, and diagrams to support the next iteration of Architecture development.
Based on TOGAF, which of the following is the best answer?

  • A. In the next iteration of Architecture development, you would describe the Target Business Architecture with a Business ServiceFunction catalog, a Business Interaction matrix, and Product Lifecycle diagrams.
    You would describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix.
  • B. In the next iteration of Architecture development, you would describe the Target Business Architecture with a Business ServiceFunction catalog, an Organization/Actor catalog, and Data Lifecycle diagrams.
    You would describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix.
  • C. In the next iteration of Architecture development, you would describe the Baseline Business Architecture with a Business Service/Function catalog, an Organization/Actor catalog, and a Data Entity/Business Function matrix. You would describe the Baseline Application Architecture with an Application/Function matrix.
  • D. In the next iteration of Architecture development, you would describe the Baseline Business Architecture with a Baseline Business Process catalog, and an Object lifecycle catalog. You would describe the Baseline Application Architecture with a Technology Portfolio catalog.

Answer: A


NEW QUESTION # 56
Scenario
Please read this scenario prior to answering the question
You have been assigned the role of Lead Enterprise Architect for a firm that produces components and
replacement parts for the automobile, electronics, and telecommunications industries. The firm has been
established for over 70 years. North America has been the primary market for its products, with just 20% of its
output being exported to Europe. The firm is planning to expand its exports to Europe and also to establish
sales in South America and the Asia Pacific region.
The firm is organized into business units that each focus on the different industry sectors. Each business unit
has acquired other producers to expand its manufacturing capacity. This has resulted in a complex
environment with a high diversity of business and manufacturing systems.
The Enterprise Architecture (EA) program within the firm has been functioning for several years.
It has made significant progress in consolidating the technology portfolio and establishing key standards. The
CIO and the COO are joint sponsors of the EA program. The EA program is mature, with an active Architecture
Board and a well-defined architecture process and standard content templates based on the TOGAF 9
Architecture Content Framework. The EA process framework is well coordinated with the PMO, Systems
Development, and Operations functions.
The firm has completed a strategic plan to reorganize its Sales & Marketing organization according to the
target geographic markets. One of the goals of this reorganization is to improve the ability of Marketing to
collect more meaningful market analytics that will enable each sector to better address market needs with
effective marketing campaigns and global product presence.
A Request for Architecture Work to address the goals of the reorganization has been approved. As the
architecture team commences its work, the CIO has expressed concerns about whether the firm will be able to
adapt to the proposed change and how to manage the associated risks.
Refer to the Scenario
You have been asked how to address the concerns of the CIO.
Based on TOGAF, which of the following is the best answer?

  • A. In Phase A, the team should analyze their risk by completing an Implementation Factor Assessment and
    Deduction Matrix to identify the particular risks associated with the implementation and deployment. The
    matrix should include a list of factors to be considered, their descriptions, and constraints that should be
    taken into account. These factors can then used to assess the initial risks associated with the proposed
    project.
  • B. In Phase A, the team should conduct a Business Scenario to identify the stakeholders1 concerns and the
    resulting requirements. Once the requirements have been identified, they can be assessed in terms of their
    risks. The risks should be evaluated in terms of how they could be avoided, transferred, or mitigated. Any
    risks that cannot be resolved should be identified as residual risks and their disposition should be decided
    by the Architecture Board.
  • C. In Phase B, the team should create a set of views that will enable them to identify the factors that will
    influence the reorganization. There should then be an assessment of each factor on a maturity scale that
    will allow the team to gauge the urgency, readiness, and degree of difficulty to fix. These factors can then
    be used to assess the initial risks associated with the proposed project.
  • D. In Phase A, the team should use the Business Transformation Readiness Assessment technique to identify
    the factors that will influence the reorganization. The assessment should include determining the readiness
    rating for each factor based on a maturity scale that will allow the team to gauge the urgency, readiness,
    and degree of difficulty to fix. These factors can then used to assess the initial risks associated with the
    proposed project.

Answer: B


NEW QUESTION # 57
Scenario:
Please read this scenario prior to answering the Question
You are the Lead Architect for a firm that manufactures ball bearings used in industrial equipment applications. They have manufacturing operations in several cities in the United States, Germany, and the United Kingdom.
The firm has traditionally allowed each manufacturing plant to drive its own production planning systems. Each plant has its own custom Materials Requirements Planning, Master Production Scheduling, Bill of Materials, and Shop Floor Control systems.
"Just In Time" manufacturing techniques are used to minimize wastes caused by excessive inventory and work in process. The increasingly competitive business environment has compelled the firm to improve its business capability to be more responsive to the needs of industrial customers. To support this capability, the firm has decided to implement an Enterprise Resource Planning (ERP) solution that will enable it to better coordinate its manufacturing capacity to match the demands for its products across all plants. In addition, there are also new European regulations coming into force to which their manufacturing processes must conform in the next six months.
As part of the implementation process, the Enterprise Architecture (EA) department has begun to implement an architecture process based on TOGAF 9. The CIO is the sponsor of the activity. The Chief Architect has directed that the program should include formal modeling using the Architecture Content Framework and the TOGAF Content Metamodel. This will enable support for the architecture tooling that the firm uses for its EA program.
The Chief Architect has stated that in order to model the complex manufacturing process it will be necessary to model processes that are event-driven. Also, in order to consolidate applications across several data centers it will be necessary to model the location of IT assets. In particular, the end goal is to have the single ERP application running in a single data center.
Currently the project is in the Preliminary Phase, and the architects are tailoring the Architecture Development Method (ADM) and Architecture Content Framework to fit into the corporate environment.
Refer to the Scenario
You have been asked to recommend a response to the Chief Architect's request to tailor the TOGAF Content Metamodel.
Based on TOGAF 9, which of the following is the best answer?

  • A. You recommend that the architecture team incorporate the Process Modeling and Governance extensions into their tailored Content Metamodel. This is suitable as this is a significant IT change that will impact its operational models. This will ensure that they include specific entities and attributes that will allow them to model the event-driven nature of the manufacturing processes more precisely.
  • B. You recommend that the architecture team incorporates the Data and Services Extensions into their tailored Content Metamodel. This would allow modeling of the location of IT assets and ensure regulatory compliance for the manufacturing process. It will also allow for identification of redundant duplication of capability which will be needed for a successful consolidation to a single data center.
  • C. You recommend that the architecture team incorporate the Process Modeling and Infrastructure Consolidation extensions into their tailored Content Metamodel. As the environment is process-centric this will enable them to model the manufacturing processes and store information to support regulatory compliance. It also includes views useful for managing the consolidation of applications into a single data center.
  • D. You recommend that the architecture team incorporates the Governance and Motivation Extensions into their tailored Content Metamodel. This would allow modeling of the target milestones they want to achieve with this consolidation of application to a single data center. These extensions will also enable demonstration of regulatory compliance for the manufacturing process.

Answer: C


NEW QUESTION # 58
......