Free 2022 PRINCE2 Agile PRINCE2-Agile-Foundation dumps are available on Google Drive shared by Prep4SureReview Welcome to download the newest Prep4SureReview PRINCE2-Agile-Foundation PDF dumps: https://www.prep4surereview.com/PRINCE2-Agile-Foundation-latest-braindumps.html ( 52 Q As) PRINCE2 PRINCE2-Agile-Foundation Exam Syllabus Topics: TopicDetailsTopic 1Understand the focus areas in an agile contexUnderstand [...]

Free 2022 PRINCE2 Agile PRINCE2-Agile-Foundation dumps are available by Prep4SureReview [Q30-Q54]

Share

Free 2022 PRINCE2 Agile PRINCE2-Agile-Foundation dumps are available on Google Drive shared by Prep4SureReview

Welcome to download the newest Prep4SureReview PRINCE2-Agile-Foundation PDF dumps: https://www.prep4surereview.com/PRINCE2-Agile-Foundation-latest-braindumps.html ( 52  Q&As)


PRINCE2 PRINCE2-Agile-Foundation Exam Syllabus Topics:

TopicDetails
Topic 1
  • Understand the focus areas in an agile contex
  • Understand key concepts relating to PRINCE2
Topic 2
  • Understand how PRINCE2 principles, themes, processes and management products are tailored and/or applied in an agile context
Topic 3
  • Understand the agile ways of working, key terms and techniques
Topic 4
  • Understand key concepts relating to projects and PRINCE2 Agile

 

NEW QUESTION 30
How does the change theme regard change in PRINCE2 Agile?

  • A. As a necessity
  • B. As disruptive
  • C. As something to be avoided
  • D. As inevitable

Answer: D

 

NEW QUESTION 31
Which is an advantage of using the PRINCE2 Agile behavior 'collaboration'?

  • A. It uses experimentation to expand requirements
  • B. It allows people to provide cover for one another
  • C. It uses learning to help improve products
  • D. It ensures that there are no surprises

Answer: C

 

NEW QUESTION 32
Which statement about the 'protect the level of quality' target is CORRECT?

  • A. It is achieved by allowing enough time for testing
  • B. It delivers the early realization of benefits
  • C. It is achieved by using the same team members
  • D. It gives confidence on the progress of the project

Answer: B

Explanation:
Reference:
%20level%20is%20met

 

NEW QUESTION 33
How is the 'tailor to suit the project' principle applied in an agile context?

  • A. By flexing what is produced to stay in control and deliver value
  • B. By emphasizing tolerances on what is being delivered
  • C. By using the Agilometer to assess the project environment
  • D. By fitting releases into planned management stages

Answer: A

 

NEW QUESTION 34
Which statement about the 'accept that the customer doesn't need everything' target is correct?

  • A. It can result in the early delivery of a minimum viable product
  • B. It allows misunderstandings to be dealt with appropriately
  • C. It is achieved by managing the culture of the team carefully
  • D. It gives confidence on the progress of the project

Answer: B

 

NEW QUESTION 35
How should product-based planning be used as part of PRINCE2 Agile?

  • A. To create the project plan using empiricism
  • B. To track progress against the team plan
  • C. To enable team planning to be predictive
  • D. To plan by focusing on the features required

Answer: D

 

NEW QUESTION 36
Which statement about velocity is CORRECT?

  • A. It is shown by the ideal line on a bum-down chart
  • B. It describes how much work is getting done
  • C. It is based on the concept of rationalism
  • D. It tracks the time and cost of a timebox

Answer: B

 

NEW QUESTION 37
Which statement about the 'directing a project' process is CORRECT?

  • A. The project board should make decisions based on the Agilometer risks
  • B. The project board should increase the stage-level time tolerance
  • C. A project board member should fulfill the product owner role within a delivery team
  • D. The project board should attend regular project progress meetings

Answer: C

 

NEW QUESTION 38
Which statement describes the Kanban approach?

  • A. It was originally focused in creating new companies and is now used to speed up product delivery
  • B. It has defined processes, products and roles used to iteratively deliver outputs using timeboxing
  • C. It is an iterative timeboxed approach that helps teams generate value
  • D. It is used to make system improvements using visualization and by controlling work in progress

Answer: D

 

NEW QUESTION 39
Which is a benefit of the Lean Startup approach to releasing a product?

  • A. It provide a technique to reduce the testing of a product before release
  • B. It reduces the number of people needed to manage a release of a product
  • C. It provides quick feedback that can be responded to at the earliest opportunity
  • D. It enables the release plans to be synchronized with the PRINCE2 plans

Answer: D

 

NEW QUESTION 40
According to PRINCE2 Agile, which form of communication shows that a team is vibrant and interactive?

  • A. Using visualization to display information
  • B. Using meeting minutes to share decisions
  • C. Using email to document discussions
  • D. Using social media to reach more people

Answer: A

 

NEW QUESTION 41
Which statement about the 'embrace change' target is CORRECT?

  • A. It minimizes the time needed to train a new team member
  • B. It reduces the planning of dependencies between projects
  • C. It reduces testing in order to meet deadlines
  • D. It encourages the customer to raise new ideas

Answer: D

 

NEW QUESTION 42
Which is a reason for releasing a product into a staging area?

  • A. It enables the faster delivery of changes
  • B. It supports management by exception
  • C. It supports regulatory compliance checking
  • D. It enables a phased Waterfall approach

Answer: C

Explanation:
Reference:
%20and%20verification%20process

 

NEW QUESTION 43
Which statement explains the target 'be on time and hit deadlines' for flexible delivery?

  • A. It enables team dynamics to remain the same
  • B. It improves the supplier's reputation with the customer
  • C. It sets the project baseline at the correct level
  • D. It reduces testing in order to meet deadlines

Answer: D

 

NEW QUESTION 44
During which process should release planning be done for the FIRST time?

  • A. Controlling a stage
  • B. Initiating a project
  • C. Managing product delivery
  • D. Managing a stage boundary

Answer: D

 

NEW QUESTION 45
Which two statements about tailoring the business case in an agile environment are CORRECT?
1. It should be unnecessary because products of the highest value will be delivered first.
2. It should identify the minimum viable product and when it will be delivered.
3. It should take into account that the scope may be reduced during the course of the project.
4. It should show the features, the order in which they will be delivered and any dependencies.

  • A. 1 and 2
  • B. 1 and 4
  • C. 2 and 3
  • D. 3 and 4

Answer: C

 

NEW QUESTION 46
Which is a key objective of running a workshop?

  • A. To encourage collaboration and create the defined outputs from the event
  • B. To make day-to-day decisions on behalf of the delivery team within a sprint
  • C. To make daily progress visible to the delivery team and key stakeholders
  • D. To communicate decisions to the wider stakeholder community

Answer: A

 

NEW QUESTION 47
Which statement explains how the 'learn from experience' principle is applied in an agile context?

  • A. It provides guidance on mapping PRINCE2 roles to an agile environment
  • B. It focuses on the prioritization and decomposition of requirements
  • C. It is supported by the 'inspect and adapt' concept
  • D. It integrates releases within management stages

Answer: C

 

NEW QUESTION 48
What should the business case state about the minimum viable product (MVP)?

  • A. That the MVP is the same as project viability
  • B. That the MVP must go into operational use
  • C. When the MVP will be defined
  • D. What the MVP is

Answer: B

 

NEW QUESTION 49
Which two statements are key responsibilities of supplier representative?
1. They highlight areas that the project may impact from a technical perspective.
2. They are partially assigned to the delivery team.
3. They create the project's specialist products.
4. They prioritize requirements.

  • A. 1 and 2
  • B. 1 and 4
  • C. 2 and 3
  • D. 3 and 4

Answer: B

 