NEW QUESTION # 36
By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?
- A. Allocate resources.
- B. Determine the project budget
- C. Establish baselines.
- D. Develop a communication plan.
Answer: C
Explanation:
Explanation
The next step after defining tasks, durations, resources, and costs is to establish baselines. A baseline is an approved version of a project plan that serves as a reference point for measuring progress and performance throughout the project lifecycle. A baseline typically includes scope, schedule, cost, quality, and risk parameters. Establishing baselines involves presenting the project plan to key stakeholders and obtaining their formal agreement on the project objectives and deliverables. Baseline approval can help to establish clear expectations, avoid scope creep, and facilitate change control during project execution34
NEW QUESTION # 37
When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?
- A. Critical paths
- B. Work breakdown structures
- C. Resources
- D. Milestones
Answer: D
Explanation:
Explanation
Milestones are activities with zero duration that are added to a project schedule by a project manager.
Milestones are significant events or achievements in a project that mark the completion of a phase, deliverable, or task. Milestones can help to track and measure the progress and performance of a project and communicate it to stakeholders.
NEW QUESTION # 38
Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?
- A. Kanban board
- B. Ishikawa diagram
- C. Decision tree
- D. Pareto chart
Answer: B
Explanation:
Explanation
An Ishikawa diagram is a tool that the project team should use to find the cause of the defects associated with project deliverables. An Ishikawa diagram, also known as a fishbone diagram or a cause-and-effect diagram, is a graphical tool that shows the possible causes of a problem or effect using a fishbone-like structure. An Ishikawa diagram can help to identify and analyze the root causes of defects or issues and find solutions to prevent or eliminate them.
NEW QUESTION # 39
After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?
- A. Notify customers.
- B. Approve the test plan.
- C. Develop a rollback plan.
- D. Implement the change.
Answer: C
Explanation:
The project manager should develop a rollback plan next after determining the appropriate maintenance window in the operational infrastructure change process. A rollback plan is a contingency plan that describes how to revert to the previous state of the system or infrastructure in case of a failure or disruption during the change implementation. A rollback plan can help to minimize the impact and risk of the change and ensure business continuity and stability.
NEW QUESTION # 40
Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?
- A. Releasing the resources
- B. Reconciling the budget
- C. Closing the contracts
- D. Evaluating the project
Answer: D
Explanation:
Evaluating the project is an activity that should be used in the closing phase of a project to support the project triple constraint. This involves reviewing the project plan, deliverables, and outcomes to ensure they meet the project objectives and requirements. References: CompTIA Project+ Study Guide Section 4.4.4
NEW QUESTION # 41
Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?
- A. Communicate with the affected stakeholders.
- B. Set a new cost using a lightweight estimation method.
- C. Adjust the scope to stay within the cost.
- D. Initiate a formal change request to modify the cost
Answer: A
Explanation:
The project manager should communicate with the affected stakeholders first after realizing that the sign-off for the project scope baseline is delayed due to multiple changes and that the budget for this project is restricted by the project sponsor. The affected stakeholders are those who have an interest or influence on the project and may be impacted by any changes or delays. Communicating with them can help to explain the situation, assess the impact, seek feedback, and manage expectations.
NEW QUESTION # 42
A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?
- A. Statement of work
- B. Master service agreement
- C. Time and materials contract
- D. Cost-plus agreement
- E. Fixed-price contract
Answer: C
Explanation:
Explanation
The project manager should put in place a time and materials contract before work begins for a third party that needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. A time and materials contract is a type of contract where the buyer pays the seller based on the actual time spent and materials used during the project. A time and materials contract is suitable for projects that have uncertain or variable scope, duration, or cost. A time and materials contract can provide flexibility and adaptability for both parties and allow them to adjust to changing requirements or circumstances.
NEW QUESTION # 43
A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?
- A. Staff directory
- B. Acceptable communication channels
- C. Responsibility assignment matrix
- D. Risk registry
Answer: B
Explanation:
Explanation
The project manager should have prepared acceptable communication channels to avoid the situation of a stakeholder not replying to emails due to intermittent Internet service. Acceptable communication channels are methods or modes of communication that are agreed upon by all parties involved in a project. They may include aspects such as email, phone call, text message, video conference, instant message, or face-to-face meeting. Acceptable communication channels can help to ensure that messages are delivered and received effectively and efficiently and that communication preferences and limitations are respected.
NEW QUESTION # 44
A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepare a report on the defects found in the previous project to avoid a decrease in production. The report shows that the two main defects are related to cosmetic and physical damage to the product. Which of the following charts would BEST prioritize which defects to address?
- A. Histogram
- B. Control
- C. Pareto
- D. Run
Answer: C
Explanation:
The project manager should use a Pareto chart to prioritize which defects to address for the product. A Pareto chart is a type of bar chart that shows the frequency or impact of different causes of problems or defects. It also shows a cumulative line that represents the percentage of the total frequency or impact. A Pareto chart can help to prioritize the causes that have the most significant effect on the quality of the product and apply the 80/20 rule, which states that 80% of the problems are caused by 20% of the causes.
NEW QUESTION # 45
For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?
- A. Project charter
- B. Resource plan
- C. RACI chart
- D. Organizational chart
Answer: C
Explanation:
A RACI chart would be the most useful option for the project manager to illustrate roles for major project activities for an upcoming project kickoff. A RACI chart is a visual representation of a RACI matrix that shows who is responsible, accountable, consulted, and informed for each task or activity in a project using a table format. A RACI chart can help to communicate and document the roles and expectations of each team member and stakeholder for the project and ensure alignment and agreement.
NEW QUESTION # 46
A program manager is reviewing the project portfolio and prioritizing each project based on the company's strategic plan. Which of the following should be considered in this evaluation? (Select TWO).
- A. Local legislation
- B. Mission statement
- C. Brand value
- D. Global environment
- E. Portfolio budget
- F. Company vision
Answer: B,F
Explanation:
Explanation
Company vision and mission statement should be considered in the evaluation of the project portfolio based on the company's strategic plan. Company vision is a statement that describes the long-term aspirations and desired future state of the organization. Company mission statement is a statement that defines the core purpose and values of the organization and how it serves its customers and stakeholders. These statements provide direction and guidance for the strategic planning and decision making of the organization. They also help to align theproject portfolio with the organizational goals and objectives and ensure that the projects and programs in the portfolio deliver value and benefits to the organization
NEW QUESTION # 47
An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?
A)
B)
C)
D)
- A. Option B
- B. Option C
- C. Option A
- D. Option D
Answer: B
Explanation:
Explanation
Option C shows a graph that most likely represents the observed relationship in this scenario. The graph shows a learning curve, which is a graphical representation of the relationship between a learner's performance on a task and the number of attempts or time required to complete the task. The learning curve theory proposes that a learner's efficiency in a task improves over time the more the learner performs the task. In this case, the IT intern was able to complete more set-ups in less time as they gained more experience and proficiency over the two-week rotation12
NEW QUESTION # 48
Which of the following software programs would be BEST to use lo store information related to business transactions?
- A. Customer relationship management
- B. Enterprise resource planning
- C. Record management system
- D. Content management system
Answer: A
Explanation:
Explanation
Customer relationship management (CRM) software would be the best to use to store information related to business transactions. CRM software is a type of software that helps businesses manage their interactions and relationships with current and potential customers. CRM software can store and organize information such as customer contact details, purchase history, preferences, feedback, complaints, etc. CRM software can help businesses improve customer service, satisfaction, loyalty, retention, and revenue1
NEW QUESTION # 49
During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?
- A. Determine budget constraints.
- B. Validate the business case.
- C. Update the project charter.
- D. Create a project schedule
Answer: C
Explanation:
Explanation
Update the project charter. Updating the project charter would be the next step for the project manager after identifying the project team during the project initiation phase. A project charter is a document that formally authorizes a project and defines its purpose, scope, objectives, deliverables, milestones, roles and responsibilities, assumptions, constraints, risks, budget, and timeline. A project charter can help to align the expectations and interests of all stakeholders involved in a project and provide direction and guidance for planning and executing the project.
NEW QUESTION # 50
A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?
- A. Milestone chart
- B. Issue log
- C. Gantt chart
- D. Change control log
Answer: D
Explanation:
Explanation
The project manager should use a change control log to document the effects of the hurricane delay on the project. A change control log is a tool that records and tracks any changes that occur during the project lifecycle. It usually includes information such as change ID, description, impact, status, approval, and resolution. A change control log can help to monitor and manage the changes that affect the project scope, schedule, cost, quality, or resources and ensure that they are aligned with the project objectives and stakeholder expectations.
NEW QUESTION # 51
During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?
- A. A change request
- B. A contingency plan
- C. A risk impact
- D. A risk budget
Answer: B
Explanation:
The project manager should have generated a contingency plan first to alleviate the impact of this issue prior to deployment where a major malfunction resulted in an inoperative product condition during a code implementation. A contingency plan is a plan that outlines alternative courses of action or strategies to deal with potential problems or risks that may occur during a project. A contingency plan can help to prevent or minimize the negative impacts of unforeseen events or issues on the project objectives and deliverables and ensure business continuity and stability.
NEW QUESTION # 52
As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?
- A. Review the backlog.
- B. Update the work breakdown structure.
- C. Establish the resource pool.
- D. Seek baseline approval.
Answer: D
Explanation:
The next step in the process after defining tasks, durations, resources, and costs is to seek baseline approval. A baseline is an approved version of a project plan that serves as a reference point for measuring progress and performance throughout the project lifecycle. A baseline typically includes scope, schedule, cost, quality, and risk parameters. Seeking baseline approval involves presenting the project plan to key stakeholders and obtaining their formal agreement on the project objectives and deliverables. Baseline approval can help to establish clear expectations, avoid scope creep, and facilitate change control during project execution.
The NEXT step after defining tasks, durations, resources, and costs during the planning phase is to seek baseline approval. Baseline approval involves finalizing the project plan and gaining approval from stakeholders, establishing the plan as the baseline for the project's performance. References: CompTIA Project+ Study Guide Section 3.4.1
NEW QUESTION # 53
Which of the following activities would a project manager perform during the closing phase? (Select THREE).
- A. Removing resources
- B. Stakeholder analysis
- C. Lessons learned
- D. Removing access
- E. Risk analysis
- F. Acquiring resources
- G. Statement of work sign-off
Answer: A,C,D
Explanation:
Explanation
Lessons learned, removing resources, and removing access are activities that a project manager would perform during the closing phase of a project. Lessons learned is a process of collecting and documenting the knowledge and experience gained from a project for future reference and improvement. Removing resources is a process of releasing or reallocating any human or material resources that were used for the project.
Removing access is a process of revoking any permissions or privileges that were granted to the project team members or stakeholders for accessing any systems or data related to the project. These activities can help to finalize and close a project successfully and ensure that all deliverables are transferred, all documentation is approved and archived, all contracts are closed, and all stakeholders are satisfied.
NEW QUESTION # 54
......